The object of compaction is to? Mark as favorite Copy Link eradicate air holes give maximum density ensure intimate contact between the concrete and the surface of reinforcement all of the above Check Answer
Vertical sides of columns may be stripped after? Mark as favorite Copy Link 1 to 2 days 7 days 14 days 21 days Check Answer
The process of hardening the concrete mixes by keeping its surface moist for a certain period called? Mark as favorite Copy Link floating curing screeding none of these Check Answer
The minimum quantity of cement to be used in controlled concrete is specified as? Mark as favorite Copy Link 120 kg/cm³ 160 kg/cm³ 220 kg/cm² 280 kg/cm² Check Answer
For compacting plain concrete or one-way reinforced concrete floors, the vibrator used is? Mark as favorite Copy Link internal vibrator screed vibrator form vibrator all of these Check Answer
The compressive strength of an ordinary Portland cement (1:3 cement mortar cube) after 7 days test should not be less than? Mark as favorite Copy Link 11 N/mm² 17.5 N/mm² 22 N/mm² 27 N/mm² Check Answer
The workability of concrete by slump test is expressed as? Mark as favorite Copy Link minutes mm/h mm²/h mm Check Answer
To perform the initial setting time test, the water is added to the cement at the rate of ………….. by weight of cement? Mark as favorite Copy Link 0.72 P 0.78 P 0.85 P 0.95 P Check Answer
To prevent segregation, the concrete should not be thrown from a height of more than? Mark as favorite Copy Link 1/2 m 1 m 1.5 m 2 m Check Answer
To perform the compressive strength test of cement, water is added at the rate of? Mark as favorite Copy Link 0.72 P+ 3% of water 0.85 P+ 4% of water P+ 3% of water P+ 4% of water Check Answer