When float or slack of an activity is positive? Mark as favorite Copy Link it represents a situation where extra resources are available and the completion of project is not delayed it represents that a programme falls behind schedule and additional resources are required to complete the project in time the activity is critical and any delay in its performance will delay the completion of whole project any one of the above Check Answer